CTE FACILITY AT RED OAK HS


Top row - Renderings; Bottom row images from July and August 2026


  • Enlarged to 90,000 sq. ft. facility will include all current CTE and kitchen with cafeteria, and room to grow

  • Pull 18-20 classes from current HS; HS campus space for core classes

  • Eliminate busing to MS CTE to prevent lost instructional time

  • $79.1 Million

ESTIMATED PROJECT TIMELINE

  • Groundbreaking in spring 2026

  • Added new student parking lot between TSTC and ROHS practice fields to replace lost parking

  • Completed Sept. 2026

  • CTE construction goal to open late fall 2027