NEW ELEMENTARY PLAYGROUNDS
New playgrounds with ADA accessibility at all five current elementary schools
Includes pathways, new ground surfaces, and all equipment
$2.2 Million
ESTIMATED PROJECT TIMELINE
Started in late summer 2025
Completed by spring 2026; added upgraded fences summer 2026 (Re-used materials from Goodloe Stadium)