TENTATIVE TIMELINE for NEW ROISD MIDDLE SCHOOL

All timeline dates are impacted by logistics, supply chain, weather, timeliness of approval process, etc.
This is a tentative timeline estimate only.

2023

  • May 6 - Bond Passed

  • May 23 - CMAR Interviews

  • May 30 - ROISD Board Approved Joeris Construction as CMAR

  • June 7 - ROISD met with Joeris Construction to discuss contract

  • June 13-Aug. 14 - ROISD programming representatives met with CORGAN representatives to discuss designs throughout updating design process

  • June 22 - ROISD agreed to terms with Joeris Construction to be the Construction manager at Risk for the NEW Red Oak Middle School

  • June 27 - Representatives from Red Oak ISD, CORGAN and Joeris Construction met with representatives from the City of Ovilla for a pre-construction meeting

  • July 11 - CORGAN representatives met with the ROISD Cabinet to discuss gathering input from designated District Staff for the construction plans

  • July 27 - CORGAN delivered preliminary site plans and construction documents for ROISD review

  • Sept. - Corgan/ROISD documents page turn review

  • Sept./Oct. - Site and Utility Early Package released for Bidding 

  • Oct. – ROISD Groundbreaking Ceremony

  • Oct./Nov. - ROISD GMP Board Approval (Site)

  • Nov. - Corgan/City Life Safety Plan Review

  • Nov./Dec. - Corgan Early Steel Package released for Bidding

  • Dec. 19, 2023 - At-Risk Grading PERMIT issued by City of Ovilla (Permit #2023-01)

  • Dec. - Joeris Construction mobilization on site 

2024    

  • Jan. 2 - City of Ovilla P&Z approved Preliminary Plat

  • Jan. 8 - Ovilla City Council approved Preliminary Plat

  • Mar. - ROISD Board Approval (Building Package)

  • Mar. - Building Pad Prep

  • June-Dec. - Exterior Construction, Begin interior

2025    

  • Jan.-Mar. - Final exterior, Interior ongoing

  • Mar. - Building Dry In

  • Mar. - Permanent Power

  • June/July - Substantial Completion

  • July/early August - Move In