TENTATIVE TIMELINE for NEW ROISD MIDDLE SCHOOL
All timeline dates are impacted by logistics, supply chain, weather, timeliness of approval process, etc.
This is a tentative timeline estimate only.
2023
May 6 - Bond Passed
May 23 - CMAR Interviews
May 30 - ROISD Board Approved Joeris Construction as CMAR
June 7 - ROISD met with Joeris Construction to discuss contract
June 13-Aug. 14 - ROISD programming representatives met with CORGAN representatives to discuss designs throughout updating design process
June 22 - ROISD agreed to terms with Joeris Construction to be the Construction manager at Risk for the NEW Red Oak Middle School
June 27 - Representatives from Red Oak ISD, CORGAN and Joeris Construction met with representatives from the City of Ovilla for a pre-construction meeting
July 11 - CORGAN representatives met with the ROISD Cabinet to discuss gathering input from designated District Staff for the construction plans
July 27 - CORGAN delivered preliminary site plans and construction documents for ROISD review
Sept. - Corgan/ROISD documents page turn review
Sept./Oct. - Site and Utility Early Package released for Bidding
Oct. – ROISD Groundbreaking Ceremony
Oct./Nov. - ROISD GMP Board Approval (Site)
Nov. - Corgan/City Life Safety Plan Review
Nov./Dec. - Corgan Early Steel Package released for Bidding
Dec. 19, 2023 - At-Risk Grading PERMIT issued by City of Ovilla (Permit #2023-01)
Dec. - Joeris Construction mobilization on site
2024
Jan. 2 - City of Ovilla P&Z approved Preliminary Plat
Jan. 8 - Ovilla City Council approved Preliminary Plat
Mar. - ROISD Board Approval (Building Package)
Mar. - Building Pad Prep
June-Dec. - Exterior Construction, Begin interior
2025
Jan.-Mar. - Final exterior, Interior ongoing
Mar. - Building Dry In
Mar. - Permanent Power
Oct. / Nov - Substantial Completion
Dec. / Jan. 2026 - Move In